The Pentagon and Congress can have little confidence in any estimate Raytheon Co. or the Air Force may offer on the cost and timeline for a troubled ground control system to operate new Global Positioning System satellites, according to a report from a nonprofit research firm.

“The program office and the prime contractor demonstrated an inability to accurately project cost and schedule,” MITRE Corp. said in the report to the Defense Department obtained by Bloomberg News.

The ground system, which was supposed to be in operation by October 2016 under Raytheon’s contract, now isn’t projected to be ready until at least April 2022, the Air Force said in July. Its projected cost has increased from $866 million in the initial contract in 2010 to $3.4 billion in November 2012 and $6.1 billion in May, according to MITRE’s report.

Buy now
Bu site deneyimlerinizi kişiselleştirmek amacıyla KVKK ve GDPR uyarınca çerez (Cookie) kullanmaktadır. Bu konu hakkında detaylı bilgi edinmek için tıklayınız.